Professor Paddle: Illabot Creek Road Closure vanlinelogistics.com Seattle Washington (WA) Warehousing & Order Fulfillment vanlinelogistics.com Seattle Washington (WA) Warehousing & Order Fulfillment vanlinelogistics.com Seattle Washington (WA) Commercial Relocation vanlinelogistics.com Warehousing & Order Fulfillment
Professor Paddle Professor Paddle
  RegisterRegister  LoginLogin
Home Calendar Forum FSBO Gallery PPages Reviews Rivers Links
  Active TopicsActive Topics  Display List of Forum MembersMemberlist  Search The ForumSearch
Whitewater Forum
 Professor Paddle : General : Whitewater Forum
Message Icon Topic: Illabot Creek Road Closure Post Reply Post New Topic
Author Message
BRoss
McNasty
McNasty
Avatar

Joined: 27 Sep 2008
Online Status: Offline
Posts: 339
  Quote BRoss Replybullet Topic: Illabot Creek Road Closure
    Posted: 30 Sep 2010 at 10:02pm
Not sure if this post is too late, but there is a couple hours left on the public comment period for the closure of the Illabot Creek Road (ends tonight at midnight). Not sure if this impacts access for the whitewater run on Illabot (never run it and likely never will). From a map posted on a hiking site, it looks like the closure would be well before Illabot Lake, which is where access is described in the Bennett book

if you have or want to run it, it is probably worth shooting a letter off to the forest service. Even if this closure doesn't affect Illabot's whitewater run, it adds to the trend of closing roads down (see MF Snoq) and that just sucks. Comments to:
Don Gay
dgay@fs.fed.us




Info below:

File Code: 1950
Date: August 30, 2010

Illabot Road (FS Road 16)     

Dear Interested Public:
The Mount Baker Ranger District of the Mount Baker-Snoqualmie National Forest is seeking comments on a proposal to decommission 14.5 miles of the Illabot Road (FS Road 16). Information about the project and possible alternatives to the proposal is provided in the enclosures. The project area is located approximately 15 miles east of the town of Concrete and 13 miles north of Darrington, Washington (Location Map). The project area is accessed by State Route 530. The legal description of the project area is: Township 34 north, Ranges 10 and 11 east.

As part of this environmental analysis process, required by the National Environmental Policy Act, I am asking those who may be interested in the proposed project for their comments and concerns. As the Responsible Official, I plan to issue an Environmental Assessment (EA) for public review in January 2011. Your comments would be most valuable if received by October 1, 2010. Comments on this project may be submitted electronically, through the mail, by fax, or hand delivered. Electronic comments may be sent to: dgay@fs.fed.us. Written comments should be sent to: Jon Vanderheyden, District Ranger, Mount Baker Ranger District, 810 State Route 20, Sedro-Wooley, WA 98284-1263. Facsimile comments can be sent by fax to (360) 856-1934. Hand delivered comments can be brought to the Ranger District Office at the above address during business hours. The Responsible Official is Jon Vanderheyden, District Ranger.

For further information regarding this project, please contact Don Gay, Interdisciplinary Team Leader, Mt. Baker Ranger District, at (360) 854-2632, or email at dgay@fs.fed.us.

If you would prefer to receive this information hard copy please contact Don Gay and he will provide it.



/s/ Jon Vanderheyden

Jon Vanderheyden
District Ranger

Comments received in response to this solicitation, including names and addresses of those who comment, will be considered part of the public record on this proposed action and will be available for public inspection. Comments submitted anonymously will be accepted and considered; however, those who submit anonymous comments will not have standing to appeal the subsequent decision under 36 CFR Parts 215 or 217. Additionally, pursuant to 7 CFR 1.27(d), any person may request the agency to withhold a submission from the public record by showing how the Freedom of Information Act (FOIA) permits such confidentiality. Persons requesting such confidentiality should be aware that, under the FOIA, confidentiality may be granted in only very limited circumstances, such as to protect trade secrets. The Forest Service will inform the requester of the agency's decision regarding the request for confidentiality, and where the request is denied, the agency will return the submission and notify the requester that the comments may be resubmitted with or without name and address within 10 days.

Project Information Letter.doc wrote:

Project Information Illabot Road

Introduction
Illabot Creek is an important anadromous fisheries resource, and is a major tributary to the Skagit River, which provides an estimated 30% of the young anadromous fish entering salt water in Puget Sound. Illabot Creek contains Chinook, coho, as well as sea-run and resident populations of cutthroat, rainbow (steelhead), and bull trout. Illabot Creek provides fish migration, refuge and rearing habitats. The Illabot main stem is accessible to steelhead and coho salmon to river mile (RM) 10.2, bull trout to RM 13.7, pink and chum salmon to RM 1.6, and Chinook salmon to RM 5.6. The main fish habitat limitations are lack of quality rearing and spawning habitat and low pool/riffle ratios in some areas. Sedimentation fills in pools, reducing their depth and/or numbers, and also affects rearing and spawning areas.

Most of Road 16 was constructed on National Forest System lands in the early 1960s to provide access for timber harvest in the Illabot Creek watershed (project map). At that time, there was no trail to Slide Lake. However a trail to Illabot Lake began on private land approximately 1.5 miles north of the National Forest boundary and followed the south bank of Illabot Creek. The Slide Lake Trail (Trail 635) was constructed after road access was created and a user created trail developed from Slide Lake to Enjar Lake. Trail access to Jordan, Falls, and Marten Lakes originated mostly from private timberlands to the north. Road closures on private land and the extension of Road 16 in the 1980s resulted in the development of the user-built trails originating from Road 16 that now access Jordan, Falls, and Marten Lakes. These trails were not constructed by the Forest Service, do not meet Forest Service trail standards, and have never been maintained by the Forest Service. However, these user built trails were added to the Mount Baker-Snoqualmie National Forest inventory of System Trails and currently are the easiest access to these wilderness lakes.

The Illabot Creek watershed east of the junction with Road 1620 is either Late Successional Reserve or Wilderness. Since there is no planned timber harvest from these areas, Road 16 beyond its junction with Road 1620 is used for trail access and dispersed recreation.

Funding is not, and has not been, sufficient to maintain all of the roads on the Mount Baker Ranger District. To adequately maintain the 505 miles of drivable roads on the District would require more than $750,000 each year. The current annual road maintenance budget is $60,000 or 8% of the need. Over the past five years special congressional appropriations such as Legacy Roads and the American Recovery and Reinvestment Act have increased the funds available for road maintenance to an average of $194,000 each year. Although these special appropriations have increase the road maintenance budget to 26% of the amount needed, they must be spent on specific roads and are only available for one year.

In the 1990s and early 2000s, limited road maintenance funds were used mostly to brush roads and maintain vehicle access on as many roads as possible and blade road surfaces to reduce potholes. As a result, maintenance of drainage structures (culverts, ditches, etc.) was not sufficiently performed, road signs were not replaced, and surfacing was rarely replaced. The insufficient maintenance of drainage structures contributed to increased rates of road damage due to storm events.

Following the national Forest Service Roads Policy of 2001, the District has been reducing the number of miles of drivable roads to address the 2001 Policy goals of a safe, environmentally sound road network that is responsive to public needs and affordable to manage. Given the declining road maintenance budget projections, only through further reductions in the total miles of road requiring maintenance can all the remaining drivable roads receive the maintenance needed to avoid flood damage and the desired level of road surfacing and signage.

Much of Road 16 was constructed at slope breaks, using excavation techniques with uncontrolled fill placement and inadequate drainage systems. The road had some drainage correction competed as recently as 1995; however, road-related fill slope failures continue to occur, and some have been noticeable contributors of sediment to Illabot Creek. Erosion and sedimentation from these events resulted in reduced water quality, burial or scouring of spawning gravels, and loss of fish habitat.

From Mile Post (MP) 10 to MP 18, Road 16 is highly susceptible to road prism slumping on the downhill side and upslope material sliding onto the road surface. Side slopes in this road segment average at least 60% with long distances of 80% to 100% slopes.    At many locations along this road segment water seeps down rock faces on the road’s uphill side into the road prism and under the road. This situation results in a high frequency of road slumps. As a result of the near surface bedrock, road fill slope failures and upslope slides are common. Repairs to these steep sections of road slopes would be very expensive and in some cases may not be repairable at all without extensive road shifts into vertical rock cliffs that are cost prohibitive.    

Because of the susceptibility of Road 16 to slumps and slides, road maintenance costs are higher for this road that other roads on the Ranger District. Although Road 16 accounts for only 2.3% of the District’s road miles, it consumes an average of 5.5% (corrected number) of the road maintenance budget. Furthermore, almost all culverts on Road 16 have exceeded their life expectancy. These culverts are undersized for adequate drainage and need to be replaced with larger culverts and additional cross-drains.    

The Mt. Baker-Snoqualmie Forest Plan, as amended, includes Forest-wide standards and guidelines direction to develop and implement projects to correct road related water quality, anadromous fish habitat, and other resource problems; and to operate, maintain, and/or close roads to meet established road management objectives and safety (Forest Plan p. 4-140).

Need for Action
There is a need for a reduction in the risk of failure of Road 16 and the resultant sediment production that would reduce water and fish habitat quality in the main stem and lower tributaries of Illabot Creek.

There is a need for a reduction in the total cost of maintaining roads on the Mount Baker Ranger District so that adequate maintenance is performed on roads remaining open to vehicle traffic.

Purpose
The purpose of the Illabot Road Project is to reduce 14.5 miles of road open to motor vehicle use and reduce annual road maintenance needs by $8,500. The purpose also includes reducing the risk of degrading water and fish habitat quality.

Proposed Action
The Forest Service is proposing to decommission 14.5 miles of the Illabot Creek Road (Road 16) from mile post 9.5 (its junction with Road 1620) to 24 (Project Map). Road decommissioning will consist of culvert removal and replacement with rocked rolling dips. Road fill slope will be stabilized by removing sidecast material and recontouring the road prism. Excess side cast material will be stored on the road bed or hauled to designated locations on spur roads or off site. Stored fill would be compacted and shaped to allow drainage. The proposal will also remove a steel bridge crossing Otter Creek for use elsewhere, and the removal of a concrete bridge over Illabot Creek that would be burried in pieces at suitable locations along the road or placed on spur roads. The Slide Lake trail and trailhead will be abandoned and removed from the Trail System Inventory. The Jordan, Marten, and Falls Lakes trails will also be removed from the Inventory.

Alternatives to the Proposed Action
1. No Action. Maintain the road in its current condition.

2. Maintain road access to the current location and reduce the risk of road failure where failure risk is highest. This alternative would involve installing rock gabion baskets or similar structures to stabilize slumping road shoulders, increasing the number and size of drainage structures, and converting three culverts to bridges.

3. Decommission up to the last 10 miles of Road 16 (from MP 24 back to MP 14.1 approximately 1 mile west of Bluebell Creek) as described in the proposed action, except retain the bridge over Illabot Creek. Reduced the risk of road failure risk as described in Alternative 2 from the National Forest boundary to MP 14.1. This alternative would convert up to five miles of the road to the Slide Lake Trail which would require placing trail bridges over several drainages after culverts are removed. In addition, a trail head would be developed at the new road terminus. The new trailhead would involve clearing less than one acre of second-growth forest and placing rock surfacing in the parking area.
"That boated a lot better than it looked." "It always does until it doesn't."
IP IP Logged Send Private Message Send Private Message
chipmaney
Big Boofer
Big Boofer
Avatar

Joined: 10 Apr 2008
Location: United States
Online Status: Offline
Posts: 591
  Quote chipmaney Replybullet Posted: 01 Oct 2010 at 9:43am
The U.S. House has passed a bill designating Illabot Creek a Wilder and Scenic River, and the bill awaits approval in the Senate. I wonder if this is related to the decision to decommission the road? The Wilder&Scenic designation would protect an area of extremely valuable salmonid habitat....
sitting all alone on a mountain by a river that has no end
IP IP Logged Send Private Message Send Private Message
Post Reply Post New Topic
Printable version Printable version

Forum Jump
You cannot post new topics in this forum
You cannot reply to topics in this forum
You cannot delete your posts in this forum
You cannot edit your posts in this forum
You cannot create polls in this forum
You cannot vote in polls in this forum